Crews from McDonald Wetle seen here installing built-up roofing at NW corner.
P&C Superintendent, Brad Esler, leads a Monday-morning on site safety meeting with trade personnel.
Structural masonry work complete and ready for structural steel.
Slab on grade placement at upper-level administration and lobby area.
Foundation work nearly complete and installation of 1st floor structural steel in process.
Lower level walls in place and work proceeding on upper level.
Footing work for upper level structure.
P&C crews are seen here working on various components of the concrete foundation system in the lower level.
Soil nails being installed to stabilize slope.
Building pad ready and foundation work ready to start.
List of key team members shown here on project sign.
Aggregate piers are being installed to support new foundation.
Mass excavation has commenced on site and temporary access road around lower level of new building is nearly complete.
City of Canby Mayor Randy Carson welcomes everyone to the Groundbreaking Event on August 11, 2011.
P&C's Project Manager Carl Grossman seen here talking with Bill Harper, Construction Manager from F. Berg.
Robert Bitter, Canby Urban Renewal Agency Project Manager thanking a community member for his support.